Gas scrubber water seal improvement and transformation method In the case of the original scrubber water seal does not move, in the scrubber Dg200 sewage valve outlet plus a water seal, water seal height slightly lower than the original water to ensure that the inlet pipe exposed liquid level. Transformation effect after transformation, the effect is obvious: 1 scrubber gas inlet pressure dropped to 4kPa, help to improve gas production. Gas scrubber outlet gas temperature <40e, fully meet the needs of the work section.
(1) Retrofit Reason 1 The distance between the blower valve and the blower box is long. After the blow-up, the gas in the tube is sometimes blown. When air is mixed, the air and gas mixture explode. The air deflagration plate is often exploded, affecting the normal production . Second on the blowing time up to 12s, corresponding to shorten the gas production time. (2) transformation method in the blow valve followed by a89 steam pipe to the hair after the valve. (3) Reforming Effect 1 After the renovation, the phenomenon of explosive plate burst when blowing air is eliminated, and the production is stabilized. Second blowing time reduced from 12s to 9s, a corresponding extension of gas production time, improve the temperament, gas.
(1) Retrofit reasons Original explosion-proof device in the replacement of explosion-proof plate, the explosion-proof plate required to remove the upper compression flange, take a long time and the explosion-proof plate compression flange and gray tank connection bolts by high temperature Disassembly difficult after running. (2) transformation of the transformation of the situation. (3) Modification effect 1 After the transformation, the outer frame and the ash bin are bolted. The flange size of the lower flange of the outer frame is the same as that of the original design compression flange. The inner frame can be removed from the outer frame. The top is bolted tightly to replace the explosion-proof plate Simply unscrew the top tightening bolt and remove or lift the inner frame, requiring less time and a good seal. Will no longer appear screw bolt phenomenon, to ensure normal production.
The above transformation after a period of operation, the effect is more obvious, but also revealed some other problems: 1, down the dust collector must be shut down to unload ash, corresponding to shorten the gas production time. If the unloading ash from the uplink dust collector to plug the valve, the uplink dust collector can achieve uninterrupted ash discharge. Such as the removal of the downstream dust collector baffle, sent to the water seal, each class flushing cans 1, without removing the dust collector, but will not affect the blowing gas.
o For a2610 above gas stove, into the furnace steam pipe using a219 can meet the production needs, yet to be implemented.